Use targeted acceleration to define the acceleration goal and the criteria for acceleration.
To run a targeted acceleration, complete the following steps:
-
Select the S4 // Acceleration tab.
-
In the Acceleration menu, click
Accelerate Schedule to display the Accelerate Schedule dialog box.
-
Optional. In the Schedule Cleanser group, select schedule cleanse options prior to running an analysis. This will enable the simulation to create a more naturally flowing and realistic schedule.
-
In the Schedule Accelerator group:
-
Select the goal (activity or project) options.
-
Select an acceleration script. If needed, click
Edit Script to edit the selected script or to create a new one.
-
Click
OK to run the simulation.